Solar Turbines Inc. commissioned gas turbine power station on offshore platform named after Yury Korchagin.

Under the contract Solar Turbines Inc. supplied four Taurus 60 gas turbine power plants each rated at 5.2 MW with efficiency of 30.4 %. They will operate in cogeneration cycle with thermal output of 9.6 MW. Three more Taurus 70 gas turbine plants will be used for the drive of compressors delivered by Dresser Rand. The output of Taurus 70 is 7.69 MW, efficiency is 34.8 %. Compressor units will be used for natural gas transportation to Makhachkala-Astrakhan cross-country pipeline.

 