TGK-14 commissioned steam turbine on the site of Ulan-Udenskaya TETs-1 thermal power station.

Tp-100/110-8,8 steam turbine was manufactured and supplied by Ural Turbine Plant. It has two cylinders with pressure of 8,8 MPa and output of 100 MW. It replaced K-100 steam turbine destroyed during the conflagration. Steam turbine power plant is equipped with TF-110 electric generator delivered by NPO Elsib. General designer of the project is Engineering Center of UES. Tp-100 steam turbine was developed on the base of Tp-115/120-130-5 and is used for thermal power stations with great load for steam extraction for central heating.