Gas engine power station was put into operation in Ramenskoye (Moscow Region).

The station will generate electric and thermal power for the needs of greenhouse complex of Teplitsy Ramenskiye Ltd. The station consists of four MWM TGC2032V16 each rated at 3.916 MW. Thermal output of each plant is 3.653 MW. The station is equipped with two waste-heat boilers. Total output of the station is 16 MW. It operates in island mode. The primary fuel is natural gas. General designer of the project is IPK ROSS. All civil, installation and commissioning works were carried out by ASK Industrial Group. The supervisor of the project is Merloni Progetti (Italy).