Trigeneration power station is under construction on the site of the pant of microwave electronics in Tomsk.

The customer of the station is Micran NPF. The main power equipment was supplied Prodex company. It is also general contractor and general designer of the project.

The station consists of two Caterpillar G3412C gas engine plants each rated at 360 kW and two Caterpillar G3508 gas engine plants each rated at 505 kW. The plants are equipped with SR4B electric generators with voltage of 0.4 kV. The station is also equipped with two KU-700 waste heat boilers each rated at 700 kW delivered by Russky Dom Ltd. and Thermax Inc. ProChill LT 31 T absorption chiller with output of 750 kW.