Combined cycle power station was commissioned on the site of Krasnodarskaya TETs.

Total electric output of the station is 410 MW. The station was designed around Mitsubishi Heavy Industries M701F4 gas turbine power plant rated at 303.4 MW, Mitsubishi Electric generator with hydrogen cooling, EMAlliance EMA-003-KU heat recovery steam generator, Т-113/145-12.4 heat extraction steam turbine manufactured by Ural Turbine Works rated at 160 MW. Total electric efficiency of the station is 57 %. After combined cycle power station commissioning the output of Krasnodarskaya TETs was increased up to 1090 MW. The cost of the project is 16 bln roubles. general contractor of the project is E4 Group JSC.

 

 