New gas turbine power station was put into commercial operation on the site of Krasnoleninskoye oil and gas field (Lukoil-West Siberia Ltd.).

The station with total output of 48 MW generates electric power for the needs of field infrastructure. It will utilize casing-head gas from the field as the fuel. Lukoil-West Siberia Ltd. is the customer and general contractor for the project. Main power equipment was supplied by Aviadvigatel JSC.

The station consists of four EGES-12S gas turbine power plants developed on the base of GTU-12PG-2 gas turbines manufactured by Perm Motor Plant. Power plants were packaged by Iskra-Energetika JSC.

 