PGU-400 was commissioned on the site of Minskaya TETs-5 (Belorussia).

PGU-400 combined cycle power station consists of Ì701F gas turbine rated at 270 MW manufactured by Dongfang Turbine Co., Ltd. under MHI license, Dongfang steam turbine rated at 129.6 MW and heat-recovery steam generator. The total cost of the project is 260.19 mln euro. The credit for the project realization was rendered by China Bank of Development. The efficiency of the station in heat extraction cycle is 57 %. The project was developed by BelNIPIenergoprom. General contractor for the project is Dongfang Turbine Co., Ltd. From Byelorussian side Belenergo RUP, Belener-gostroy JSC and Belenergoremnaladka JSC took part in the realization of the project.