The construction of Novo-Bereznikovskaya power station in Permsky Area.

The station will be constructed and commissioned by KES-Holding JSC. It will consist of two General Electric MS6001FA gas turbine power plants each rated at 77 MW and two UTZ steam turbines. Total electric output of combined cycle cogeneration power station will be 230 MW. Commissioning of Novo-Bereznikovskaya power station is planned at the end of 2015. The cost of the project is 10 bln rubles. At present practically all main power equipment was delivered to the site. Modular transformers were developed and supplied to the station by Toghliatti transformers Ltd.