New power stations will be constructed on Yaregskoye and Usinskoye oil fields (Lukoil-Komi).

General designer and general contractor of the project is Lukoil-Energoengineering Ltd. Power units will be developed, produced and supplied by Aviadvigatel JSC. GTES-25PA plants each rated at 25 MW are developed on the base of PS-90GP-25 gas turbines. They will operate in cogeneration cycle and will use associated petroleum gas as the main fuel. They will be equipped with hot-water waste-heat boilers. In total seven GTES-25PA power plants with overall electric output of 175 MW will be supplied to the sites. Their commissioning is planned in 2015-2016.