The output of power station on the site of Khancheyskoye oil field was increased.

Taurus-Energy Ltd. supplied two OP16-3A gas turbine plants (OPRA Turbines B.V.) each rated at 1.8 MW to the site of Khancheyskoye oil field under the contract with Novatek-Tarkosalneftegas Ltd. The station operates in simple cycle. Main fuel is associated petroleum gas from gas condensate field. The construction of the station was carried out by consortium including Energoservice JSC and Turboenergia and Service Ltd. General contractor for the project is Energoservice JSC. New OP16-3A plants are synchronized with two earlier commissioned OPRA gas turbine plants and three GE Jenbacher gas engine plants. In future it is planned to increase total electric output of the station up to 7.2 MW.