Solar Turbines Inc. compressor units were installed on the site of Vyngapurovsky gas processing plant.

Under the contract Solar Turbines Inc. supplied two Centaur 50 CS and three Mars 100 CS compressor units. They operate as a part of technological train for natural gas processing on the site of Vyngapurovsky gas processing plant (SiburTyumenGas JSC).

Centaur 50 CS compressor unit was developed on the base of Centaur 50 gas turbine engine and C33 compressor. Mars 100 CS compressor unit was developed on the base of gas turbine engine and C51 and C61 turbocompressors. Mars 100 CS compressor units operate in parallel to each other. Gas pressure is increased 0.35 up to 7.6 MPa and from 1.35 up to 7.76 MPa and also from 5.24 up to 7.75 MPa.