Total electric output of Zhanazholskaya GTES-45 was increased.

The project was realized by SNPS Aktobemunaygas JSC under the program of complete utilization of associated petroleum gas. Under the project two steam turbine units were added to existing three GE-10/1 gas turbine plants. Three CG-330/9.81-Q heat recovery steam generators and two EHNK 71/90/160 with total electric output of 160 MW were installed on the site. Additional electric power will be used for technological needs of SNPS Aktobemunaygas JSC departments and supplied to national power grid.