Associated petroleum gas is utilized for power supply of oil wells on the site of Sorovskoye field.

The tender for power equipment delivery to the site of Sorovskoye field was won by Aggreko Eurasia Ltd. Under the contract Aggreko supplied gas engine power plants with total electric output of 5.5 MW. It is planned to increase the output of power station up to 12 MW. Power plants use associated petroleum gas as the main fuel. The project was realized by Aggreko on turn-key basis. All commissioning works were carried out by general contractor during 3 days.