Iskra-Energetika JSC supplied power plants to the site of Chayandinskoye oil & gas condensate field

They were delivered to the site under the order of Gasprom dobycha Noyabrsk Ltd. Total electric output of the station is 72 MW, thermal output – 80.4 MW. It will operate in cogeneration cycle. The station wil consist of six EGES-12S Ural power plants developed by Iskra NPO and manufactured by Iskra-Energetika JSC. EGES-12S Ural power plant was designed around GTU-12P developed by Aviadvigatel JSC and manufactured by Perm Motor Plant and TS-12 electric generators supplied by Privod JSC.