Power Machines PJSC signed the contract for modernization of two power units of Norilskaya TETs-2

Turn-key contract was signed with Norilsky Nikel. Under the contract Power Machines will reconstruct two power units of Norilskaya TETs-2 with complete replacement of main and auxiliary equipment. The scope of equipment delivery for each power unit will include steam extraction turbine rated at 130 MW equipped with electric generator manufactured by Power Machines, steam boiler with output of 500 tons per hour manufactured by Krasny Kotelshchik (Taganrog), two unit transformers with capacity of 160 and 250 MVA manufactured by joint venture of Power Machines and Toshiba. The commissioning of the 1st power unit of the station is planned in 2020, of the 2nd unit in 2022. In result the reliability and commercial efficiency will be increased.

Дата публикации: 
Mon, 07/10/2017
Хранить в архиве: 
Xранить