Eight power plants are in operation on the site of Vostochno-Messoyakhskoye field

Power plants on the site of Vostochno-Messoyakhskoye field

The stations are installed on the sites of multiple-well platforms of Vostochno-Messoyakhskoye licensed site in Tazovsky District of Yamalo-Nenetsky Autonomous Area. General contractor and supplier of the main power equipment for the project is Volgaenergoprom TSK. In total 15 diesel power plants were delivered for 8 power stations. They were developed on the base of Cummins diesel engines and Mecc Alte electric generators with voltage of 0.4 kV.