Second stage of Yamal LNG plant is commissioned.Yamal LNG plant is joint venture of independent gas producer Novatek JSC, French company Total SA and Chinese fund The Silk Road. The project is realized near Sabetta sea port. LNG plant with output of 16.5 mln tons per year is under construction on the site of Yuzhno-Tambeyskoye gas condensate field. Technological equipment for three production lines on the plant was supplied by GE Oil & Gas. Each production line includes two main refrigeration units for gas liquification. Refrigeration unit consists of Frame 7EA gas turbine rates at 86 MW, three centrifugal compressors (two compressors with combined cooling agent and one propane compressor), variable-frequency starting system and energy recovery system with output of 24 MW, waste-heat recovery unit, necessary auxiliary equipment. In total GE Oil & Gas supplied six Frame 7EA gas turbine plants, eighteen centrifugal compressors, six variable-frequency electrical drives and six waste-heat boilers.
Дата публикации:
Thu, 11/01/2018
Хранить в архиве:
Не хранить >>
|
Search |
|
© Все права защищены, ООО «Турбомашины», 2005-2024.
Вся информация, опубликованная на веб-сайте turbine-diesel.ru, является интеллектуальной собственностью ООО "Турбомашины". Никакие опубликованные на сайте материалы не могут быть воспроизведены в той или иной форме печатными изданиями, телеканалами и радиостанциями без ссылки на журнал "Турбины и Дизели", а другими сайтами, в т.ч. сетевыми СМИ, не могут быть использованы без активной гиперссылки на turbine-diesel.ru и ссылки на журнал "Турбины и Дизели". При воспроизведении опубликованных материалов письменного разрешения от администрации настоящего сайта не требуется.
Ответственность за содержание размещенных на веб-сайте рекламных объявлений, в т.ч. баннеров, несет исключительно рекламодатель. За содержание сайтов, на которые приводятся гиперссылки, ООО "Турбомашины" ответственности не несет.
|