The output of gas engine power station at Tsarichanskoye field in Orenburgskaya Region was increased.

The first stage of the station with electric output of 5 MW was commissioned in 2014. The project was realized under the program Gas-Orenburg. Then ten more power plants were installed on the site on a staged basis. At the end of last year extra three power plants each rated at 1 MW were commissioned on the site. At present 18 Caterpillar G3516 gas engine power plants are in operation on the site. The plants were supplied by Vostochnaya Technika and Mantrak Vostok.