The eighth Ladoga gas pumping unit was delivered to the construction site of the Amur gas processing plant.

The gas pumping unit is being installed as part of the fourth production line. The first seven units have already been installed, and stage-by-stage preparations for commissioning are underway. Two units are installed on each booster compressor station of the production line. After extracting valuable fractions from the raw gas for further processing in Russia, the Ladoga gas pumping units will compress the purified methane for further supply along the Eastern Route.