An 8 MW power complex for a mining farm has been built in the Penza region.

Electrosystems has completed the construction of a gas turbine power plant with a total capacity of 8 MW for a mining farm in the Penza region for the company Electriсservis. As part of the project, containerized power units and auxiliary equipment were manufactured at Electrosystems own productionfacilities.
The GPES includes four power units based on LY2000GL-T gas piston units manufactured by Liyu Gas Power with a unit capacityof 2 MW and an output voltage of 0.4 kV.

Дата публикации: 
Thu, 12/11/2025
Хранить в архиве: 
Не хранить