PGU-210 combined cycle power station was commissioned on the site of Novgorodskaya TETs.

Full-scale testing of the station was carried out by TGK-2. As the result of testing the station confirmed all design parameters and was put into operation. PGU-210 combined cycle power station was developed on the base of GTE-160 gas turbine plant and heat-recovery steam generator. Main power equipment for the project was supplied by Power Machines JSC. The company also carried out installation and commissioning works. The total cost of the project is 6 bln RF rubles. After commissioning total electric output of Novgorodskaya TETs was increased from 200 up to 350 MW.