Adlerskaya TETs operates on the full load.

Total electric output of the station is 360 MW, thermal output of 264 MW. General contractor of the project is TEK Mosenergo. The station was developed on the base of four Ansaldo Energia V64.3A gas turbine power plants, four E-99.6/14.5-7.71/0.55-545/21 heat recovery steam generators supplied by Podolsky machine-building plant and two Kaluga turbine plant T-48/62-7.4/0.12 steam turbines equipped with TZFP-63-2MUZ 9 electric generators manufactured by Power Machines JSC. The commissioning of Steam turbine power plants was carried out by Lonas Technology JSC. Adlerskaya TETs is the biggest plant constructed under the program of preparation for international sporting contests of 2014.