Energoteh Company will construct power station on the site of Vologodsky Bearing Plant.

Under the turn-key contract Energoteh Company will construct power station with total electric output of 4 MW for reliable power supply of the enterprise. Modular power station will consist of two MWM TCG 2020V20 gas engine power plants. They will be equipped with waste heat utilization systems. Furthermore, Energoteh will carry out modernization of electrical equipment and reconstruction of engineering communications and the construction of new electrical connections. The station will be equipped with automatic control system developed on the base of Energosoft hardware and software complex. The commissioning of the station is planned at the beginning of the next year.