New boiler-house on biomass was commissioned in Latvia.

Liepajas energija boiler-house and CHP plant commissioning gave the opportunity to reduce electricity tariff by 22% and to increase enterprise efficiency by 28%. New boiler-house is equipped with two modern hot-water boilers each rated at 15 MW. They use wood chips as the fuel. CHP plant was commissioned in 2012. It is equipped with Turboden 22 CHP (Rankin Cycle) with electric output of 2320 kW. Generated thermal power is used in central heating system of the city, electric power is transferred to national power grid. The station was developed by UPB. Main power equipment was supplied by Turboden (Italy) and Kohlbach (Austria).