T Plus Company takes part in the construction of Kazanskaya TETs-1

T Plus Group signed the contract with Uralenergostroy Managing Company for the construction of two power units of Kazanskaya TETs-1 with total electric output of 230 MW. The customer of the project is Generating company JSC (Tatarstan Republic). General contractor of the project is Uralenergostroy, general designer of the station is Energoprogress engineering center. T Plus Group will carry out engineering support of the project, commissioning of the equipment.

Each power unit of the station will comprise of GE Frame 6FA gas turbine plant rated at 75 MW, Uralsky turbine plant steam turbine with electric output of 40 MW and EMAlliance heat recovery steam generator. The commissioning of combined cycle power station on the site is planned up to the April of 2018.