Under the contract with Gasprom dobycha Yamburg, Ltd. UEC-Gas turbines will manufacture and supply four GTN-16R-PS gas pumping units. They will be installed on the site of booster compressor station at Zapolyarnoye oil and gas condensate field. Earlier in 2016-2018 UEC-Gas turbines produced and delivered GPA-16 gas pumping units to the site. The units were developed on the base of PS-90GP-2 gas turbine drives manufactured by UEC-Perm motors. The units are equipped with centrifugal compressors with magnetic bearings supplied by REP Holding. Changeable flow channels of the compressors are equipped with dry gas seals and rotor magnetic levitation. It eliminates mechanical friction and improves reliability of the units. Hangar type gas pumping units will be commissioned in 2021. At present there are 13 units in operation at the site. General designer of the project is Saratovsky affiliate of Gasprom projectirovanie, Ltd.

The project included construction of combined cycle power station with total electric output of 409 MW, dual electric power transmission line 220 kV and reconstruction of transmission lines. All construction works were carried out by Toyo Engineering Corporation (Japan). Single-unit power station was developed on the base of M701F gas turbine plant.