Новости

Novogrudskaya wind parkGrodnoenergo RUP has finished the construction of Novogrudskaya wind park. Electric output of the wind park is 9 MW. At present it is the most powerful wind park in Byelorussia. It consists of five HW2/S1500 (87) and one HW82/1500 wind turbines each rated at 1.5 MW. Power equipment for the park was supplied by Huayi Electric Apparatus Group. The park was constructed near Grabniki settlement. General designer of the project is Belenergosetproject RUP, general contractor is Belelectromontazhnaladka RUP.

15/09/2016

Pyakyakhinskoye oil & gas condensate field, GTES-24The second unit of the station consists of two Ural-6000 gas turbine plants each rated at 6 MW. They were developed and manufactured by Aviadvigatel JSC (Perm). The customer of the equipment is Lukoil – Western Siberia (TPP Yamalneftegas).
Container power station was constructed beyond the Arctic Circle in the conditions of deep-frozen soil. Power plants were installed on the piling field at a height of 3 meters from the ground. Temperature rage in the region is –60…+45 °C.

12/09/2016

Under the contract UEC-Gas Turbines JSC will supply two GTA-6RM gas turbine power plants. New power equipment will be able to operate in island mode and in parallel with existing power system of field. GTA-6RM plants were developed on the base of gas turbine engines manufactured by Saturn NPO.

15/08/2016

The project was realized by Intma Group of Companies under turn-key contract. The second stage of the station consists of seven GE Jenbacher JMS 620 GS gas engine power plants each rated at 3356 kW, thermal output is 3095 kW.

The equipment has to be supplied to the customer in the middle of 2015. After commissioning of the second stage of the station total electric output of the station will be increased up to 46.9 MW, thermal output up to 42.9 MW.

All generated electric and thermal power will be used for the needs of the Maysky green-house complex. The station can operate on the base mode in parallel with the main power grid of Maysky green-house complex.

12/08/2016

Two out-of-date boiler houses in Kasli and Karabash were updated on the base of gas engine power plants. Wartsila supplied and commissioned two 20V34SG power plants for each site. Electrical output of 20V34SG power plant is 9.73 MW.

Power plants were constructed under Regional program for municipal central heating system modernization. The projects were realized by Perspektiva private investment company which is the owner of power stations.

05/08/2016

Under the contract KMPO will supply three GPA-16 hangar type gas pumping units to Nortgas JSC. The units were developed on the base of NK-16ST gas turbine engines. They will be equipped with 43GTs2-158/33-104 centrifugal compressors which will be supplied by Kazankompressormash JSC. The cost of the contract is 2.2 bln of rubles. They will operate on the site of Severo-Urengoyskoye oil & gas condensate field.

18/07/2016

The station consists of three ENEX 65 microturbine plants equipped with waste-heat boilers. Total electric output of the station is 195 kW. Thermal output of the station is 345 kW. It is transferred to core circuit of peak boiler house.

13/07/2016