The plants will be installed on the site of Vyborzhets agricultural company. They will generate electric and thermal power for green-houses with total area of 36 ha. The first stage of the station will consist of four JMS 624 GS gas engine power plants each rated at 4 MW. The station will operate on island mode without synchronization with main power grid. All generated electric and thermal power will be used for the needs of green-house complex. The commissioning of the first stage of the station is planned at the end of 2012. In future three similar power plants will be added to the station. The commissioning of the second unit of the station is planned in 2013. Vyborzhets agricultural company is situated near Saint-Petersburg.

Biogas power plant rated at 1.4 MW was built in Lan village (Nesvizh District, Minsk Region). It was designed around GE Jenbacher. Container power plant was installed on the open site. The station will operate in cogeneration cycle. The company will generate electric energy from the biogas produced from organic waste. 