Новости

Alstom has signed two modernisation contracts in Poland worth approximately €15 million. The first contract signed on 28 March 2012 with Elektrownia “Kozienice” S.A.consists of upgrading steam turbine units no 3 and 6 of the Kozienice power plant. The scope of the project will include exchanging blades and diaphragms, revitalising steam turbine casings and valve chambers and multiple equipment overhauls.

This modernisation project marks several key benefits for Poland’s second largest coal-fired power station with an installed capacity of 2820 MW. As a result of the upgrades, the Kozienice power plant will benefit from an increase of power output by 3MW per unit, an efficiency increase for the high-pressure turbine and lifetime extension.

Earlier in February 2012, Dalkia Łódź S.A awarded Alstom the contract to perform a series of upgrades to units no 3 and 4 of the Lodz cogeneration heat power plant. With an installed capacity of 1671MW, the coal-fired Lodz plant will receive major turbine generator set overhauls, new high-pressure steam turbine modules and other equipment upgrades. Modernisation will result in an increase of the steam turbine generator sets’ efficiency, power and availability.

24/04/2012

WinWinD has installed six WWD-3 wind turbines in wind parks located in the municipalities of the Fiefs and Sains-lès-Pernes in France. All turbines are now mechanically installed, and two turbines have been connected to the grid. Site operations will continue with electrical installations, commissioning and test runs. The hub height of the turbines is 88 m and the rotor diameter is 103 m.

 

23/04/2012

The output of the station is 20 bln m3. The total cost of the project realized by Turkmengas Concern is more than 132 mln euro. Dovletabad-2 was constructed under turn-key basis by ENEX Process Engineering Ltd. (Belgium). Three Vectra-40 gas pumping units each rated at 30 MW were delivered by Dresser Rand Company. Dresser Rand gas turbines are equipped with GE Energy gas generators. Gas pumping units are installed in separate buildings of hangar type.

19/04/2012

The station was constructed in Vostok settlement, Kustanayskaya Region. The customer of the station is Karaman-K Ltd. The project was developed by Zorg Biogas Ukraine. The station consists of two Tedom Cento T180 SR each rated at 180 kW. The plants are installed in separate building. Generated thermal power is used for biogas production.

17/04/2012

Power station operates on the site of Orenburgburneft JSC. It consists of six FG Wilson Ð635 diesel power plants supplied by Hited-Ural company under turn-key contract. Total electric output of the station is 3 MW.

18/04/2012

Stroemberg JSC is the customer for the project, Prodex is general designer. General contractor is TOR Company. Total electric output of the station is 10.9 MW, thermal capacity – 26 MW. The station was designed on the base of 6 JMS 612 GS-N.LC engines.

16/04/2012

Siemens is again to deliver state-of-the-art power plant technology to South Korea. For the Ansan combined cycle power plant (CCPP), the company is supplying the Power Island consisting of two innovative SGT6-8000H gas turbines, one steam turbine, three generators, and two heat recovery steam generators as well as the entire instrumentation and control technology.

Ansan is now the second power plant in South Korea to be equipped with the new gas turbines – SGT6-8000H – from Siemens. The customer is the South Korean Posco Engineering & Construction Co. Ltd., headquartered in Incheon, which is responsible for construction of the entire plant. The CCPP Ansan will be fueled with liquefied natural gas (LNG) and will have a gross installed electrical capacity of 834 megawatts (MW) at a gross efficiency of 61 percent. In addition to generating electricity, the plant will also provide district heating for the inhabitants of the city of Ansan, which raises the overall fuel utilization factor to over 75 percent. Commissioning is planned for the end of 2014.

10/04/2012