Vestas China has received its very first V100 turbine order from Datang Hubei Renewable Energy (Datang Renewable). The introduction of the newest addition to the 2 MW platform in China took place in early 2011. The order represents not only an important step further into the low wind regime in China, but also a step into the new geographical market of the Hubei province.

The 27 units of V100-1.8 MW turbines with a total capacity of 48.6 MW will be installed in the Long Ganhu wind farm in the Hubei province, a low-wind site with an average wind speed at 5 m/s. Compared to other wind power plants in China, the Long Ganhu site is situated close to one of the intensively energy consuming areas of Hubei province. Thus, this answers the call from the National Government of pursuing the development of “distributed” wind power in China. The successful application of Vestas’ V100 at this wind site will set an example for distributed wind power at low-wind sites in other provinces, and the open-up in the Hubei province will bring new business opportunities for Vestas.

20/02/2012

The customer of the station is Micran NPF. The main power equipment was supplied Prodex company. It is also general contractor and general designer of the project.

The station consists of two Caterpillar G3412C gas engine plants each rated at 360 kW and two Caterpillar G3508 gas engine plants each rated at 505 kW. The plants are equipped with SR4B electric generators with voltage of 0.4 kV. The station is also equipped with two KU-700 waste heat boilers each rated at 700 kW delivered by Russky Dom Ltd. and Thermax Inc. ProChill LT 31 T absorption chiller with output of 750 kW.

17/01/2012

The station was constructed under the contract with Saturn Ltd. – manufacturer of metal furniture for storages and warehouses. The station consists of two Capstone C65 microturbine power plants each rated at 65 kW. They are equipped with waste heat utilization systems. Generated thermal power is used for facilities heating.

 

 

20/01/2012

The project of the station construction was developed by Eneka consulting company. General contractor for the project is Promenergoservice. The main power equipment was supplied by MT Technologies (Saint-Petersburg).

The station consists of five Capstone C200 microturbine power plants each rated at 200 kW. Total electric output of the station is 1000 kW, thermal output is 1860 kW. The station operates on base mode in parallel with main power grid. Natural gas is the main fuel for the station.

 

 

18/01/2012

The station consists of two power units with total electric output of 1238 kW. The first power unit was designed around two Petra 500C gas engine power plants each rated at 405 kW. They were designed around MAN E2842 LE 322 gas engine and Leroy-Somer electric generators. The plants are equipped with waste heat boilers.

10/01/2012

The unit consists of two Waukesha APG1000 gas engine power plants each rated at 1 MW. The plants were designed around 16V150LTD gas engine and Leroy-Somer 54.1-VL10 electric generator with voltage of 0.4 kV. The plants are equipped with Enalco waste heat boilers. The project was developed by Melian Company. General contractor for the project is Teplitsenergostroy Ltd.

 

 

16/01/2012

Power station is situated in Takhtamukay settlement. The customer of the project is Tander JSC. The station consists of five Petra 2500C gas engine power plants each rated at 1986 kW. The plants are designed around MWM TCG 2020 V20 gas engines and Marelli Motori electric generators.

 

11/01/2012