Новости

The wind turbine manufacturer has now signed a contract with Midtfjellet Vindkraft, which is owned by utility Ostfold Energi, local utility Fitjar Kraftlag and the independent power producer (IPP) Vardar, for the delivery and installation of 21 N90/2500 wind turbines. The contract also includes a five-year premium service agreement with an option for renewal by up to further ten years.

The “Midtfjellet” wind farm is being built on the Norwegian island of Stord. Work on installing the 52.5 MW project is to commence in summer 2012, with completion scheduled for 2013.

At the site off the Norwegian Atlantic coast, climatic conditions are relatively mild thanks to the influence of the Gulf Stream, meaning that winter temperatures rarely drop below -10 °C. On the other hand, heavy turbulence on the hilly and sparsely vegetated Midtfjellet plateau and good wind conditions with speeds averaging 8.8 m/s call for very robust and proven strong-wind turbines. The 21 turbines will be able to generate over 170,000 MWh of clean electricity per year.

15/12/2011

The station will operate on casing-head gas. It will consist of four Capstone C200 microturbines. Total electric output of the station will be 800 kW. Casing-head will be supplied to microturbines just after separator because the microturbines can use the gas with high sulfur content as a fuel. It will substantially reduce capital costs of the station. The station will operate in island mode together with existing Capstone C30 microturbine commissioned in 2007. The customer of the equipment is Tatneft JSC. Under the contract BPC Engineering will deliver the equipment and will carry out construction, engineering and commissioning works.

 

14/12/2011

Intma JSC, official distributor of GE Jenbacher, is realizing the project of gas engine power station under turn key contract. The output of the station will be 24 MW. It will be commissioned in Satka (Chelyabinskaya Region). The station will consists of six GE Jenbacher JMC 624 each rated at 4034 kW. They will operate in parallel with main power grid.

13/12/2011

K-110-1.6 steam turbine was tested during 72 hours with nominal load of 110 MW. It operates on waste steam from existing P-100-130/15 Ural Turbine Works steam turbine. At present both steam turbines operate in parallel. As a result total electric output of Tobolskaya TETs thermal power station was increased by 210 MW and now it is 662 MW.

 

12/12/2011

GTES Ural-6000 gas turbine power plants will be installed on the site of Yaraktinskoye oil field and will generate power for the needs of field infrastructure. Total electric output of the station will be 12 MW. The main fuel for the station will be casing-head gas. Ural-6000 gas turbine power plants will operate in simple cycle without waste heat utilization.

08/12/2011

The station was designed around Siemens AG SCC5-4000F 1o1 single-shaft gas turbine combined cycle power plant. It consists of SGT5-4000F gas turbine rated at 286.6 MW, heat-recovery steam generator and Siemens steam turbine. PGU-400 net efficiency is 56.6 %. Total cost of the project is 16.6 billion roubles.

General contractor for the project is ENKA Insaat ve Sanayi A.S. (Turkey). As a result total electric output of Yajvinskaya GRES thermal power station was increased from 600 up to 1000 MW.

 

07/12/2011

The station consists of three Caterpillar G3520C gas engine plants each rated at 2 MW. They are equipped with Caterpillar SR4B HV electric generators with voltage of 10.5 kV and Frerk Aggregatebau GmbH waste-heat boilers with cycle water temperature 70/90 °C. The main fuel for the station is natural gas. Main power equipment was supplied by Zeppelin Russland.

16/12/2011