Новости

The power plant with the capacity of 44 MW will be built by Iskra-Energetika JSC in Znamensk, Astrakhan Region. The project will be realized under the turnkey contract. The power plant will be designed on the base of two GTE-16PA2 power units. Heat-recovery steam generators will be manufactured by Belenergomash boiler plant, steam turbine - by Kaluga turbine works.
The customer and investor for the project is Eurasia-Energo Company, the general designer is Giprokislorod JSC. The commissioning is scheduled for 2010.

 

08/05/2009

The project is realized under Moscow energy program. The power unit is based on two Siemens SGT-800 gas turbine units rated at 45 MW each, P-108 heat recovery steam generators manufactured by ZiO-Podolsk and Siemens SST-400 steam turbine rated at 40.5 MW. At the beginning of April the power unit passed successful 72-hour testing at nominal load.
Under the reconstruction of Strogino power plant they plan to install a new power block with the capacity of 261.4 MW consisting of two units. The commissioning of the second unit is scheduled for the current year. The power block will operate on base load with the efficiency 52.6%.
The new power plant will provide electric power for Krasnaya Presnya main road, adjacent house-building areas and enterprises in Moscow northwest district.

Auxiliary power source will improve electric and thermal power supply of Strogino district. The application of up-to-date gas turbine power units will minimize harmful exhaust in the atmosphere.

The general designer for the project is TEPengineering company, the power equipment supplier is Electrozavod JSC. Installation and commissioning of the power unit was carried out by Karat RSK.

23/04/2009

Acceptance testing and presentation of a new multifunctional power complex on the base of AVE-250S wind power unit rated at 250 kW were carried out at Zapolyarnaya wind farm in Vorkuta.
The power complex consists of separate modules. Multifunctionality is provided by the possibility to produce from local resources engine fuels or producer gas for electric and thermal power generation. The problem of electromagnetic compatibility of wind generating sets with local network systems and diesel generators was also solved. The prototypes of such power complexes on the base of wind and diesel power plants are planned to be built in Tiksi town of Yakutia and Baranchinsky settlement in Sverdlovsk Region.

 

25/04/2009

Siemens Energy has been awarded a contract to supply four simple cycle gas turbine packages for the Cleveland County generating plant near Grover in North Carolina. The purchaser of the equipment is Birmingham-based Southern Power, a subsidiary of Southern Company, which provides power to the Southeast. The plant will be able to generate approximately 720 megawatts at the summer peak and is scheduled to come on line in early 2012.
The Siemens scope of supply for the Cleveland County Plant encompasses four SGT6-PAC-5000F gas turbine packages, including service contracts. Each package consists of a SGT6-5000F gas turbine, air-cooled generator, auxiliaries, the innovative SPPA-T3000 control system and an option for the exhaust stack. The fast-start capability of the SGT6-5000F gas turbine will allow Southern Power to deliver power to the grid quickly, while also helping to keep per start emissions low.

27/04/2009

It’s one of the greatest power projects realized on the territory of Belorussia. At 420 MW power plant the first stage of 100 MW was replaced by 230 MW combined cycle power unit. As a result total electric output of the power plant was increased up to 550 MW.
The customer for the project is RUP Minskenergo, the general contractor is Belenergostroy JSC. The reconstruction project was developed by RUP Belnipienergoprom.
The power unit was designed on the base of Alstom Power Systems GT13E2 gas turbine with the capacity of 170 MW. It also includes double-pressure steam boiler by SES Energ Ya.s. and T-53/67-8,0 cogeneration steam turbine by Ural Turbine Works. The power unit operates in parallel to the power grid.

28/04/2009

The commissioning is scheduled for the end of the year. Gross station output will be increased up to 158 MW. The capacity of the first stage in operation is 78 MW.
SGT-700 gas turbine power units and SST-600 steam turbine unit manufactured by Siemens Industrial Turbomachinery have already been delivered. The installation of the power equipment will begin in the nearest future.
The general contractor for the project is GlobalElectroService JSC. The cost of the project is 4.2 billion rubles.

 

01/05/2009

At present the power plant operates on the base of two power units equipped with DTc59 engines rated at 12 MW each and two UGT 16000 power units with the capacity 16.3 MW each manufactured by Zorya-Mashproekt, NPKG. The fuel is casing-head gas.
Under the third stage two UGT 16000 power units with the capacity 16.3 MW each and the efficiency 31.5 % were delivered. The power units are equipped with TS-20 generators manufactured by Privod JSC.
By 2010 three more analogous power units are scheduled for commissioning. The general designer for the project is Energotechprom Ltd. Yuzhtransenergo, AK, JSC will handle installation and commissioning. The customer is AMF-Group.

20/04/2009